The Transmission Company of Nigeria (TCN) has commenced the construction of a turn-in-turn-out along the 330kV Jos-Bauchi-Gombe transmission line to connect the new Bauchi 330kV Transmission Substation to the grid.
A statement by Ndidi Mbah, GM, Public Affairs, said work began on it on June 10, 2025, and is expected to be completed by June 14, 2025.
During the construction period, the statement disclosed that the Gombe and Biu Transmission Substations will receive power through the Dadin-Kowa Hydro Power Plant and Maiduguri Substation, supported by the Maiduguri Emergency Power Plant (MEPP).
"As a result, there will be a temporary reduction in bulk electricity supply to Jos and Yola Electricity Distribution Companies for onward distribution to their customers in Bauchi, Gombe, Ashaka, Savannah, Damaturu/Potiskum, and Biu.
"Only Yola and Jalingo will, however, experience full power outages during the five-day project duration."
A new transmission tower, it said, is also being installed to enhance the resilience and flexibility of the network, allowing the Bauchi and Gombe Substations to act as mutual backups in the event of maintenance or fault.
"Additionally, Jos will be able to supply Bauchi Substation directly through a 132kV transmission line whenever the primary 330kV connection via Gombe is unavailable.
"This arrangement enhances power reliability, diversifies transmission routes, and improves emergency response efficiency.
"TCN remains committed to strengthening Nigeria’s electricity infrastructure to facilitate a more stable and effective bulk power supply.
"The company appeals for the patience of affected consumers during the period and assures that normal electricity delivery will resume immediately after the project’s completion." it stated